# Run a production

To run a production, click **Run Production** in the production console. After you click Run Production, the status bar updates with the following stages and fields as the documents produce:

![An image of the Production status bar showing a production being run.](https://help.relativity.com/RelativityaiR/Content/Resources/Images/Features/Production_sets/SCR_ProductionConsoleProducing.png)

- **Cleaning Existing Files** - deletes placeholder files (slip sheets) and any produced image files from a prior run production, if necessary.
- **Creating Placeholder Images** - creates placeholder images based on the production data source.
- **Creating and Applying Bates numbers** - creates and applies Bates numbers based on your production numbering.
- **Creating Branding Queue Records** - creates branding queue records for later review.

> **Note:** In the viewer, you can view the produced images by selecting the Production mode. You can view the images exactly as they were produced.

## Checking production status

During the production step, a report is available in the Status section. Use this report to quickly identify the number of documents, images, redacted documents, etc.

### Production Summary fields

![An image of a Production Summary.](https://help.relativity.com/RelativityaiR/Content/Resources/Images/Features/Production_sets/SCR_production-summary.png)

Production Summary fields include:

- **Begin Bates**—Lists the Bates number of the first document in the production set.
- **End Bates**—Lists the Bates number of the last document in the production set.
- **Total Docs**—Lists the number of documents included in the production set.
- **Total Images**—Lists the number of images included in the production set.
- **Docs With Images**—Lists the number of documents that include images included in the production set.
- **Docs With Natives**—Lists the number of documents that include natives included in the production set.
- **Docs With PDFs**—Lists the number of documents that include stored PDFs in the production set.
- **Docs With Placeholders**—Lists the number of documents that include placeholders included in the production set.
- **Documents With Redactions**—Lists the number of documents that include redacted images and redacted natives included in the production set.

- **Total Image size in GB**—Lists the size of images in GB.
- **Run Date**—Lists the date of when the production was run.

### Branding Summary fields

![Branding a production](https://help.relativity.com/RelativityaiR/Content/Resources/Images/Features/Production_sets/SCR_BrandingSummary.png)

Branding Summary fields include:

- **Start Time**—Lists the start time of branding.
- **Branding Completion**—Lists the time of completion for branding.
- **Completion Rate**—Lists the progress of branding.
- **Estimated Time Remaining**—Lists the amount of time left in branding.

### Post Production Summary fields

![An image of a Production status bar in the Post Production stage.](https://help.relativity.com/RelativityaiR/Content/Resources/Images/Features/Production_sets/SCR_post-production-summary.png)

Post Production Summary fields include:

- **Copy Bates to Document Fields** - lists the progress of the step.